| Single skin profiled steel sheeting and over purlin celotex board lining panel replaced using 820 sq. metres of 80mm thick Corus Panels and Profiles Merlin Grey Trisomet composite panels incorporating Bret Martin factory assembled rooflights. |
 |
| New timber purlins were hammer fixed to the existing concrete purlins with fisher fixings. 80 linear metres of existing internal concrete gutters were bypassed with new eaves hung plastisol coated steel units by extending the length of the roof sheeting. New air handling fans and permanent venting cowls were installed to provide fresh air flow within the gymnasium. |
|
|